ODOT accelerates bridge project
- Written by Oregon Business Team
- Published in High Five
- 0 comments
When it came time to replace a bridge on Oregon Route 213 in Oregon City, a project team that included the Oregon Department of Transportation decided they couldn't afford to shut down traffic for an entire year.
Instead, they will replace the bridge using a relatively new technique called accelerated bridge construction.
Accelerated bridge construction is a showstopping technique in which hydraulic lift equipment is used to slide a preconstructed bridge into place. The complexity of the method and a lack of understanding about when and where it should be used have limited ODOT’s use of accelerated construction for only 15 bridge projects so far.
“Imagine driving down a bridge on a Friday and then driving over a new bridge Monday without ever knowing it,” [ODOT preservation managing engineer Benjamin] Tang said. “We’re working to build the industry towards this. As people become savvier, it will become a conventional practice.”
Read more at the Daily Journal of Commerce.
{biztweet}accelerated bridge{/biztweet}
Latest from Oregon Business Team
- Energize + Grow Your Workforce: Employee Commute and Remote Work Support + Benefits Options
- Make getting to work a perk by tapping into no-cost employee vanpooling services
- 2023 100 Best Companies to Work For in Oregon Happy Hour Awards Celebration
- Workplace Wellness and Active Commutes
- 100 Best Companies Merchandise